Airlift powered pond build by Smetjen

Here you can find some good examples of Airlift powered ponds.

Airlift powered pond build by Smetjen

Postby Pssymon » Thu 25 May 2017, 3:12:02

The second pond build to be shared on the site, is by user Smetjen (Geert).
This is a very clean build as well. After sharing some ideas on the forum the floor-plan was adjusted and the build could be finalized.




Airlift powered pond build, by Smetjen


The updated plans that were created with help from the forum members:

Image
Image

Image

This is the floor plan drawn to scale. In the top left there will be an Airlift which only purpose is to create a good current in the pond and if possible, move floating debris into the skimmer. Three bottom drains will be installed, one of these will be aerated. The shallow area is created because this area is very close to the neighbours' house which could be risky when digging.

The filter floor plan:

Image

The three bottom drains all connect to the first chamber which will also house the skimmer. A valterra 90mm valve is installed at the bottom of the skimmer so it can be closed and the chamber and drains can be cleaned.
In the extra chamber there will be another transit which will allow the placement of a trickle filter in the future, which will connect to the moving bed filter. The pond will run with one Airlift with a secoh SLL-40 pump which should give enough flow. A second transit will be built in just in case one Airlift is not enough.


Image

This is the section view of the chamber with the Airlift and the control room. The chambers all connect to each other with three 125mm transits to be absolutely sure there is not too much drag. The Collector will be built in two parts, as this would otherwise be in the way during the build as it will be enclosed in the concrete floor. The concrete floor will be poured in one go as this is the cheapest way to do it. Afterwards it will be covered with a cement floor. Every chamber will have a 90mm drain pipe and will connect to a chamber with a pump to get rid of the dirty water.



Image

Section view of the chamber with the japanese matting and the moving bed. The matting will not be aerated (for now) as this water directly flows from the moving bed where it has been aerated already.
The (future) trickle filters' drain will also connect to the moving bed chamber, this will have a VDL valve as the trickle won't run in winter and this could cause trouble when it's freezing.


Image

The section view of the first chamber and the static bed chamber. Here two 200 micron Crielsieves will be placed which each will have a 160mm transit into the static bed.
This chamber will also house the skimmer with the Valterra 90mm valve, as mentioned before. Below the feeding valve another valve will be placed with a detachable coupling.



A picture of one of the first purchases for the project:

Image

This will serve as a temporary home for the fish.
This big pool will also allow for a large amount of the current pond water and bacteria to be used again to start up the new pond.



After some tips on the forum, the plans were adjusted again.
The second outlet will now become an inlet for the filter. An Airlift in the last chamber, running on a 30w air pump, will run this. Together this should give about 26000 litres of flow through the filter.
The skimmer will get its own Airlift as well, running on a 20w pump. This should improve flow through the three drains as the 40w pump now only has to run these without the added skimmer.



The demolition of the old pond has started, these are some pictures of the way it looks now:


Image

The reeds have to be removed as the drainage system will be placed and these are in the way.


Image

The pond will just become 10cm wider, as much more than that would cause it to no longer match the sliding door.
It will be built 130cm into the terrace however, so it will be closer to the house. At the other side it will become 20cm longer.
The entire pond will also be raised to 30cm above ground level to prevent leaves blowing into the pond.
The fish will have to stay in their temporary home for about two months while the build is finished.

Image


Later, the drainage system is installed.
It's advised to place the system 10-14 days before digging starts to be sure that groundwater will not be an issue.

Some pictures from that morning, first the holes had to be handmade with a soil auger to get to the required depth. (Geert in the picture below)

Image

After that, the filters can be connected to the main suction line going to the pump.

Image
Image

Now the pump can start running. It will take over 10 days before the digging will start from this point.
Before that the pond and a part of the terrace will be removed.


The PVC pipes and bends have been delivered. It's amazing to see how much goes into the pond.

Image
Image

This is almost everything, just the two Collectors and two Airlifts that have already been made are not in the pictures.
The next day work is continuing on preparing the garden. The fish are staying in the pond as long as possible due to freezing temperatures at night.




Continuing work on removing part of the terrace.

Image

All 1470 bricks have been brushed clean by hand as these are going to be used to create a new path next to the finished pond.



This afternoon the building blocks were delivered a day early, which meant they had to be moved by Geert alone.

Image
Image

After asking where the blocks had to go, and being told that everything had to go through the garage into the garden, the driver wished him good luck with it.

Image

All blocks had to be moved by wheelbarrow through the garage into the garden.

Image

Image

Image


Continued in part two!
User avatar
Pssymon
 
Posts: 89
Images: 7
Joined: Fri 11 Dec 2015, 0:12:51
Location: The Netherlands

Re: Airlift powered pond build by Smetjen

Postby Pssymon » Wed 12 Jul 2017, 4:12:35

Part two:


After moving a lot of the blocks with his dad, it's time for a break.

Image

The neighbours and Geert's wife coming to help:

Image
Image


This is what's left after moving blocks for 4 hours. The rest is done the next day.

Image


A picture of how the garden looks at this point:

Image


Now the time has come to completely remove the old pond before the new hole is dug.
First the temporary pool is filled.

Image

Moved the Koi from the pond into the pool:

Image

4 of the Koi are moving out, the rest is staying.


The pond has been pumped out and cleaned. The Oase pump is visible in the photo, which has been running for 10 years. This big energy consumer is no longer needed as it will be replaced with an Airlift!

Image


Removing the liner and underlay.

Image


Then the old concrete had to be removed, which turned out to be a serious job.

Another photo of how the hole looks at this stage. Everything between the orange stakes has to be dug down to 165cm.

Image

Before the digging started, Geert dug a hole 10cm deeper than the required depth, to test the drainage system's effectiveness.
Luckily there was no ground water seeping up at all, so everything was looking good for the dig.



The next day at 8AM, digging started:

Image


The ditch had to be filled so the digger could cross:

Image
Image


After digging for about an hour, the first problem arises. There are a couple of cables in the way...

Image


After a lot of phonecalls and chatter, a technician showed up to check the cables.

Image
Image

One of the cables needed to be checked by a different technician, causing even more delays.
But then luckily, the cables can be removed as they are no longer in use!

Image
Image


Here Geert checks the depth of the hole. He used a waterlevel to set a couple of reference points and attached a cord so he could check the depth.
You can also see the first part of the structure which will become the temporary roof over the pond.

Image
Image
Image
Image


Finally at the point where the pond is almost entirely dug out. The final bits in the corners have to be dug by hand as the view from the digger is limited here.

Image
Image


The construction of the roof continues. Nylon cords are tensioned over the frame to prevent sagging of the plastic roof.
Not ideal, but hopefully this is enough to protect the build from the bad weather.

Image


Now everything is dry and protected, and the bottom drain locations can be marked.

Image


The first bit of piping can be placed. A lot of careful thought and measuring has to be done to prevent any problems that can arise later.

Image


After making sure everything is placed correctly and the bottom drain is level, it's partly dug in to make sure it does not move at this point.

Image

Later the drain and pipe were completely covered and the sand around the pipe was compacted.

Image


Continuing with the piping, gluing, measuring, cutting...

Image


Unexpected help arrives (Geert's dad). This is very welcome as the work has to be finished before the concrete is being delivered.

Image


Placing the skimmer drain. This will all be pressure PVC as a precaution.

Image

Geert built a template to neatly house the 3 bottom drain- and skimmer pipes. This way they cannot move when the concrete is poured and you end up with a nice precise placement.

Image


Here you can see the chimney pot which is placed a bit deeper and sits on 4 spacers. This is done so it will nicely seal when the concrete is poured. The reason this is placed here is because this will become the lowest point of the filter pit. A submersible pump will be placed here, which will effectively pump out all of the waste water.

Image
Image


This morning the Collector's were placed. The one in the back is only 1 meter high, this will be figured out later since it's going to be placed inside the pump chamber.

Image

At this point everything that will be under- and inside the floor has been placed.
Everything is made as level as possible with a rake. Then some plastic foil is placed to contain the concrete and prevent the moisture from seeping into the ground during the curing process.
Two layers of reinforcement are placed as the pond is situated above an old waterway.

Image


Here, everything is ready for the concrete to be poured. Placing the reinforcement was finished just 30 minutes before the concrete truck arrived.

Image

Geert's dad worrying about the whole thing. :)

Image

The pump truck has arrived:

Image

Shortly after that the concrete truck also arrived with the required 7,5m³ of concrete.

Image



This was taken after the concrete was all poured. An important milestone in the build.

Image
User avatar
Pssymon
 
Posts: 89
Images: 7
Joined: Fri 11 Dec 2015, 0:12:51
Location: The Netherlands

Re: Airlift powered pond build by Smetjen

Postby Pssymon » Wed 11 Oct 2017, 18:27:33

Part 3



After the floor has been poured, a friend of Geert came to help establish the height that the pond should become, by using his laser leveler.

Image

Image

Since it was still early in the day after that, the bricklaying was started.

Image


The first out of 1270 blocks.

Image


A couple of blocks on:

Image

The result in the evening after a couple of hours of bricklaying:

Image


This is after another day of bricklaying. In the picture you can see half hollow blocks that have been placed sideways. This is done so the rebar can be extended into these hollow blocks before pouring the raised plateau which will be situated here. This should provide some extra strength.

Image

A picture from the other side of the pond:

Image

Cutting one more block:

Image



Since the wind was an issue, the roof had to be dismantled.
Between the downpours work was continued. The first layer of the filterpit was finished together with the required drain pipes.

Image

The materials for the shallow area were delivered as well.

Image




The plastic and rebar is placed so the floor can be made. The pictures show how the rebar is put inside the hollow block to connect and strengthen everything.

Image


A 315mm PVC tube is used to get the concrete where it needs to be, without damaging the pond edges and surroundings.

Image

The result after one night of drying:

Image


There are some worries about the huge mess.

Image


A few days later things are starting to look better as more rows of blocks are added to the walls.

Image



The weather forecast predicted more rain to come, so the roof had to be redone again so the bricklaying could continue at a fast pace.
This time the plastic roof was tightened to the frame some more to prevent wind damage.

Image


After another day's work Geert was back on schedule:

Image

Image

The result after another day working in the 'pit' as it was called:

Image



Some pictures of how the blocks were moved on to the floor:

Image

Image


Since the tube that supplies the Collector will run alongside this wall over a 10 meter length, some supporting blocks are placed to make sure the tube cannot break or sag.

Image


Test fitting the bends. This will make glueing everything together easier:

Image


Now everything can be glued together. The Collector transit sticks out 3-4cm into the Collector (more than enough). The transit has been sealed on the inside with some glue as well.

Image


This photo shows how the tube will be placed. The area behind the wall has been filled with sand up to the level of the supports (about 1,2m between them).

Image

This was done before the wall was made to full height, as that would make the tubes difficult to reach and glue.



Another row has now been placed and the shallow area is looking better.

Image


The filter is now reaching a height where it's difficult to step over the walls, so some old boards are used to get around.

Image


Now the walls are at the height where the dry area in the filter needs some openings fitted for electricity, tapwater, the submersible pump, etc.

Image

Image


The current wall height:

Image


The shallow area which now needs two more rows of blocks.

Image


The start of the last row:

Image


This is the point where the first skimmer has to be built into the wall, shown on the picture here. As you can see this has been modified to fit a 110mm pipe since this will be running on an Airlift!

Image


The downside of all the progress is that it's getting more and more difficult to get around without hitting your head on the temporary roof. Measuring is becoming more of a challenge as well.

Image


In the foreground of the picture above you can see two large pipes that are partly built into the wall already. These will become the transits behind the Crielsieve which will lead to the static bed. These pipes are 160mm in diameter to be absolutely sure they won't be a bottleneck.


The board which was used as a block slide will have to go now as the wall has to be finished.

Image


Nearly there!

Image



Here the skimmer and the trickle return have been fitted. The trickle filter is a plan for later, just the preparations are made in advance so it can be easily installed later without having to go through the wall again. Behind the wall a VDL knife valve will be used with a watertight cap at the end to make sure this will never leak.

Image


At this point one side of the pond + the filter compartments need one more row of blocks before the second skimmer can be placed.

Image


The skimmer is now placed, and if all measuring was done right this should all line up perfectly.

Image


This marks the end of all the bricklaying activities which is a big relief.
The pond is now cleaned up, since there is some time in the day left a start is made with the plastering:

Image



After starting the plastering, Geert decided to try and finish plastering the entire pond the next day. This worked well untill work on the second wall started, and the plaster started to nearly fall off the wall...

Image

Image


After a day of looking for the solution, Geert asked the forum and received some tips.
Then the plastering continued. Starting with the filter compartments this time. This wasn't as easy as expected, especially when you're a tall guy.
The transits in these small spaces don't help much either.
After one and a half days work on the filter is done. The polyestering will be done by a specialist later.

Image

Image

Two chambers showing the transits that are in the way a lot:

Image

Image


For a change some more bricklaying has to be done.

Image



Here a large part of the pond has been plastered, which is a much easier job than the filter compartments!

Image

Some beer to keep spirits up..

Image




After plastering was finished, it was time to apply the surface finish (screed) layer in the pond and filter chambers.

Image


The first load of screed is ready to be applied. In total about 4,5m³ has to be moved to the pond with the wheelbarrow.

Image


To be able to reach the bottom of the filter compartments, some creativity was needed to properly reach everything.

Image

A couple of hours later the surface finish is competely done. Another step closer to the end.

Image

The look of the pond really changed after this layer. The shallow area looks much better now. This area slopes down 23cm on a length of 135cm. This should be steep enough to prevent debris settling.

Image


A view of the first filter chamber where the bottom drain and skimmer connect to. In the middle you can see the drain.

Image


Another picture of the finished layer in the pond:

Image

This layer now needs to dry for 14 days before the polyester layer can be applied.
User avatar
Pssymon
 
Posts: 89
Images: 7
Joined: Fri 11 Dec 2015, 0:12:51
Location: The Netherlands

Re: Airlift powered pond build by Smetjen

Postby bryanangler » Fri 27 Oct 2017, 0:06:54

Dude your progress is fantastic. Thank you so much for sharing this!
bryanangler
 
Posts: 3
Joined: Wed 16 Mar 2016, 14:46:21
Location: North Carolina, USA

Re: Airlift powered pond build by Smetjen

Postby Pssymon » Mon 06 Nov 2017, 18:15:57

Thank you for your comment Bryan, I will let Geert know when the topic is complete. If you have any further comments or questions feel free to add them here.
User avatar
Pssymon
 
Posts: 89
Images: 7
Joined: Fri 11 Dec 2015, 0:12:51
Location: The Netherlands


Return to Airlift powered ponds

Who is online

Users browsing this forum: No registered users and 1 guest

cron