This is a very clean build as well. After sharing some ideas on the forum the floor-plan was adjusted and the build could be finalized.
Airlift powered pond build, by Smetjen
The updated plans that were created with help from the forum members:
This is the floor plan drawn to scale. In the top left there will be an Airlift which only purpose is to create a good current in the pond and if possible, move floating debris into the skimmer. Three bottom drains will be installed, one of these will be aerated. The shallow area is created because this area is very close to the neighbours' house which could be risky when digging.
The filter floor plan:
The three bottom drains all connect to the first chamber which will also house the skimmer. A valterra 90mm valve is installed at the bottom of the skimmer so it can be closed and the chamber and drains can be cleaned.
In the extra chamber there will be another transit which will allow the placement of a trickle filter in the future, which will connect to the moving bed filter. The pond will run with one Airlift with a secoh SLL-40 pump which should give enough flow. A second transit will be built in just in case one Airlift is not enough.
This is the section view of the chamber with the Airlift and the control room. The chambers all connect to each other with three 125mm transits to be absolutely sure there is not too much drag. The Collector will be built in two parts, as this would otherwise be in the way during the build as it will be enclosed in the concrete floor. The concrete floor will be poured in one go as this is the cheapest way to do it. Afterwards it will be covered with a cement floor. Every chamber will have a 90mm drain pipe and will connect to a chamber with a pump to get rid of the dirty water.
Section view of the chamber with the japanese matting and the moving bed. The matting will not be aerated (for now) as this water directly flows from the moving bed where it has been aerated already.
The (future) trickle filters' drain will also connect to the moving bed chamber, this will have a VDL valve as the trickle won't run in winter and this could cause trouble when it's freezing.
The section view of the first chamber and the static bed chamber. Here two 200 micron Crielsieves will be placed which each will have a 160mm transit into the static bed.
This chamber will also house the skimmer with the Valterra 90mm valve, as mentioned before. Below the feeding valve another valve will be placed with a detachable coupling.
A picture of one of the first purchases for the project:
This will serve as a temporary home for the fish.
This big pool will also allow for a large amount of the current pond water and bacteria to be used again to start up the new pond.
After some tips on the forum, the plans were adjusted again.
The second outlet will now become an inlet for the filter. An Airlift in the last chamber, running on a 30w air pump, will run this. Together this should give about 26000 litres of flow through the filter.
The skimmer will get its own Airlift as well, running on a 20w pump. This should improve flow through the three drains as the 40w pump now only has to run these without the added skimmer.
The demolition of the old pond has started, these are some pictures of the way it looks now:
The reeds have to be removed as the drainage system will be placed and these are in the way.
The pond will just become 10cm wider, as much more than that would cause it to no longer match the sliding door.
It will be built 130cm into the terrace however, so it will be closer to the house. At the other side it will become 20cm longer.
The entire pond will also be raised to 30cm above ground level to prevent leaves blowing into the pond.
The fish will have to stay in their temporary home for about two months while the build is finished.
Later, the drainage system is installed.
It's advised to place the system 10-14 days before digging starts to be sure that groundwater will not be an issue.
Some pictures from that morning, first the holes had to be handmade with a soil auger to get to the required depth. (Geert in the picture below)
After that, the filters can be connected to the main suction line going to the pump.
Now the pump can start running. It will take over 10 days before the digging will start from this point.
Before that the pond and a part of the terrace will be removed.
The PVC pipes and bends have been delivered. It's amazing to see how much goes into the pond.
This is almost everything, just the two Collectors and two Airlifts that have already been made are not in the pictures.
The next day work is continuing on preparing the garden. The fish are staying in the pond as long as possible due to freezing temperatures at night.
Continuing work on removing part of the terrace.
All 1470 bricks have been brushed clean by hand as these are going to be used to create a new path next to the finished pond.
This afternoon the building blocks were delivered a day early, which meant they had to be moved by Geert alone.
After asking where the blocks had to go, and being told that everything had to go through the garage into the garden, the driver wished him good luck with it.
All blocks had to be moved by wheelbarrow through the garage into the garden.
Continued in part two!